Современные проблемы промышленного и гражданского строительства на занятиях английского языка. Кузьмина Е.В. - 18 стр.

UptoLike

Составители: 

18
according to his plans and that the materials specified in the contract are being
used. During the building period, the client pays the bills from the contractor.
Subsequently, the contractor completes the building and the client occupies it.
For six months after completion there is a period known as the ‘defects liability
period’. During this period, the contractor must correct any defects that appear
in the fabric of the building. Finally, when all the defects have been corrected,
the client takes full possession of the building.
Now find a word or an expression in the passage which means:
a) to be given the job of designing a building
b) to offer to a client for his consideration
c) to combine into a whole
d) to offer to do some work at a certain price
e) to look at the building work in detail at regular intervals
f) named or described exactly
g) an interval of time after the building has been finished during which the
contractor is responsible for correcting any faults in it
h) to have complete ownership of the building
8. Discussion: Your ideas about the material.