133
RisklD
: Testproj-079
State:
CLOSED
Date Originated:
1999/03/05
Originator:
Guy Merritt
Owner:
Joan Hoigard
Owner e-mail:
Impact Severity:
30 Work Days
Risk Exposure:
4.50
Impact Type:
Schedule Impact
Risk Factor:
0.92
Risk Event Risk Impact
Prototype build for ABC module on the
Surface Mount Technology (SMT) line will
not be completed by April 20, 1999.
Firmware unit testing for the ABC module will
delayed by six weeks.
Event Drivers Impact Drivers
1. SMT line is scheduled for
replacement during the prototype build for the
ABC module. Time required for replacement
is six weeks.
1. Firmware Unit testing activity for A3C
module is on the critical path.
2. Firmware Unit testing requires ABC module.
Probability of Event
(Pe):
0.3 Probability of Impact
(Pi):
0.5
Prevention Plan 1 Contingency Plan 1
Due Date:
March 9 1999
Due Date:
April 101999
Date Completed:
March 29 1999
Date Completed:
April 141999
Owner:
Joan Hoigard
Owner:
Bob Maher
Plan the replacement for the SMT line to
occur four weeks earlier to allow the ABC
module to be built on time. We need to
contact the vendor.
Develop a hardware emulator to allow unit
testing to continue without the A3C module.
Status 1
Status 1
March 29, 1999: SMT line vendor is not able
to install earlier due to other customer
commitments.
April 6, 1999: A simple emulator has been
developed. It appears that 85% of the firmware
functions can be tested without the ABC module.
Notes:
April 10, 1999: Risk Event occured and Firmware unit testing has been completed using the
hardware emulator. Resultant schedule slip will only
be
4 work days. May 10, 1999: Prototypes
have bean built and the last 15% of testing
has
been completed.
Closure Data
Actual Closed Date:
May 101999
Actual Impact:
4 Work Days
Disposition of Risk Disposition of Risk
Event:
Occured
Impact:
Mitigated
L
ast Modified: 1999/03/05
Рис. 9.7. Web-версия плана работы фирмы по конкретному риску